Quintana Roo Systems
Site
Name
Installation Date
System Size
in kW
Direct Beneficiaries
Indirect Beneficiaries
Project
Type
El Cardenal
October 1996
1.13
5
13
PV- Water Pumping/ Livestock
Santa Teresa
Building 1
November 1996
0.08
30
300
PV- Electrification
Santa Teresa Radio
Communication
November 1996
0.15
30
300
PV-Communications
Santa Teresa
Building 4
November 1996
0.08
30
300
PV- Electrification
Electrification
Santa Teresa
Building 3
November 1996
0.08
30
300
PV- Electrification
Santa Teresa
Building 2
November 1996
0.11
30
300
PV- Electrification
Costa de Cocos
November 1996
10.00
9140
91400
Wind- Electrification
Santa Teresa-Work
Room Power
November 1996
0.30
300
30
PV- Electrification
Santa Teresa
Building 5
November 1996
0.11
30
300
PV- Electrification
Chumpon Water Pumping
December 1996
0.05
5
13
PV- Water Pumping/ Domestic
San Eric Water
Pumping
December 1996
0.05
8
20
PV- Water Pumping/ Domestic
El Ramonal - Radio
Repeater
December 1996
0.45
100
1000
PV-Communications
Pulticub Water
Pumping
December 1996
0.05
4
10
PV- Water Pumping/ Domestic
Pulticub Radio
Repeater
December 1996
0.45
100
1000
PV-Communications
Pulticub Outdoor
Light
December 1996
0.15
4
40
PV- Electrification
Pulticub Radio
Communication
December 1996
0.11
4
40
PV-Communications
Pulticub Building
December 1996
0.05
4
40
PV- Electrification
San Eric Outdoor
Lighting
December 1996
0.15
8
80
PV- Electrification
Chunyaxche Vivero
December 1996
0.11
6
15
PV- Water Pumping/ Irrigation
Chumpon Radio
Communication
January 1997
0.11
5
50
PV-Communications
Chumpon Outdoor
Light
January 1997
0.15
5
50
PV- Electrification
Santa Teresa Water Pumping
January 1997
0.15
30
75
PV- Water Pumping/ Domestic
Chumpon Building
January 1997
0.05
4
40
PV- Electrification
Chunyaxche
Building
January 1997
0.05
6
60
PV- Electrification
Santa Teresa
Outdoor Light 1
January 1997
0.15
30
300
PV- Electrification
Santa Teresa
Outdoor Light 2
January 1997
0.15
30
300
PV- Electrification
Chunyaxche Radio
Communication
January 1997
0.11
4
40
PV-Communications
Chunyaxche
Outdoor Light
January 1997
0.15
4
40
PV- Electrification
Chunyaxche Water
Pumping
January 1997
0.05
6
15
PV- Water Pumping/ Domestic
San Diego
May 1997
0.20
1
3
PV- Water Pumping/ Livestock
La Virtud
May 1997
0.40
1
3
PV- Water Pumping
Las Pulgas
May 1997
1.80
1
3
PV- Water Pumping
Flor de Jazmin
May 1997
0.10
1
3
PV- Water Pumping
Rancho Leydi Sofía
October 1997
0.10
4
10
PV- Water Pumping/ Livestock
Rancho Maravilla
October 1997
0.10
6
15
PV- Water Pumping/ Livestock
Rancho San Isidro
November 1997
0.14
4
10
PV- Water Pumping/ Livestock
Rancho Chico
November 1997
0.10
4
10
PV- Water Pumping/ Livestock
Rancho El
Cabrónomo
November 1997
0.07
25
63
PV- Water Pumping/ Livestock
Rancho La Sabana
November 1997
0.10
4
10
PV- Water Pumping/ Livestock
Rancho El Cabo
December 1997
0.10
5
13
PV- Water Pumping/ Livestock
Rancho X-Campana
December 1997
0.10
5
13
PV- Water Pumping/ Livestock
Rancho Emiliano
Zapata
December 1997
0.10
5
13
PV- Water Pumping/ Livestock
Rancho Nueva York
de San Judas
Tadeo
December 1997
0.14
3
8
PV- Water Pumping/ Livestock
Rancho Villa de
Leyva
December 1997
0.14
5
13
PV- Water Pumping/ Livestock
Rancho La Cuchilla
del Tesoro
December 1997
0.07
2
5
PV- Water Pumping/ Livestock
Rancho El Chechén
December 1997
0.14
4
10
PV- Water Pumping/ Livestock
Rancho Pichol
January 1998
0.21
5
13
PV- Water Pumping/ Livestock
Rancho Santa
Dorita
January 1998
0.28
4
10
PV- Water Pumping/ Livestock
Rancho Yax-Hol
January 1998
0.20
4
10
PV- Water Pumping/ Livestock
Rancho El Lejano
Oriente
January 1998
0.20
4
10
PV- Water Pumping/ Livestock
Rancho San Jorge
January 1998
0.14
2
5
PV- Water Pumping/ Livestock
Rancho El Valle del
Zumbido
January 1998
1.12
5
13
PV- Water Pumping/ Livestock
San Manuel
January 1998
0.10
2
5
PV- Water Pumping/ Livestock
X-Calak
August 1998
1.50
300
750
Wind- Water Pumping
Mi Tuch
December 1998
0.21
5
13
PV- Water Pumping
San Miguel III
December 1998
0.21
5
13
PV- Water Pumping
La Ceiba
December 1998
0.16
5
13
PV- Water Pumping
Arizona
December 1998
0.16
5
13
PV- Water Pumping
La Candelaria
December 1998
0.16
5
13
PV- Water Pumping
El Chacte
December 1998
0.21
5
13
PV- Water Pumping
Nuevo Horizonte
December 1998
0.16
5
13
PV- Water Pumping
Tres Reyes II
December 1998
0.21
5
13
PV- Water Pumping
Los Tres Cerros
December 1998
0.16
5
13
PV- Water Pumping
San Rafael
December 1998
0.21
5
13
PV- Water Pumping
El Mostrenco
December 1998
0.16
5
13
PV- Water Pumping
El Esfuerzo
December 1998
0.16
5
13
PV- Water Pumping
Las Cotorras
December 1998
0.16
5
13
PV- Water Pumping
El Cometa
December 1998
0.21
5
13
PV- Water Pumping
El Sat
December 1998
0.16
5
13
PV- Water Pumping
El Escondido
December 1998
0.16
5
13
PV- Water Pumping
La Loma
December 1998
0.16
5
13
PV- Water Pumping
Santa María
December 1998
0.20
5
13
PV- Water Pumping
Parque Nacional
Isla Contoy
December 1998
0.256-PV 1.0 -Wind
300
3600
Hybrid
(PV and Wind)
Yum Balam
December 1998
0.50
10
100
Wind- Electrification
Pez Maya
December 1998
0.80
30
300
Wind- Electrification

Back to Top
Back to Installed Systems Page

(Baja California Norte) (Baja California Sur) (Chiapas) (Chihuahua) (Coahuila) (Jalisco) (Michoacán) (Morelos) (Oaxaca) (San Luis Potosí) (Sonora) (Veracruz) (Yucatán)